ISO/IEC 17025 (2017)
Infrastructure and Asset Integrity
Service | Product | Determinant | Technique | Procedure | Limitations |
---|---|---|---|---|---|
Establishment of annex facilities | Materials defined by all or some for which the site is accredited | Determinations defined by all or some for which the site is accredited | Techniques defined by all or some for which the site is accredited | ||
Evaluation of geotechnical and civil construction material - Aggregate contaminants | Aggregates | Clay and fine silt; Weak particles contaminants | Settling; Sieve analysis | AS 1141.32, AS 1141.33, TfNSW TS 02799.43 | |
Evaluation of geotechnical and civil construction material - Aggregate properties | Aggregates | Particle size distribution | Sieve analysis | AS 1141.11.1, RMS (NSW) Method T201 TfNSW TS 02799.02 | |
Particle size distribution | Fine particles in road materials | AS 1141.19 | |||
Particle density of coarse aggregate; Particle density of fine aggregate; Water absorption of coarse aggregate; Water absorption of fine aggregate | Weighing-in-water | AS 1141.5, AS 1141.6.1, TfNSW TS 02799.07, TfNSW TS 02799.08, TfNSW TS 02799.09 | |||
Bulk density | Compacted; Uncompacted | AS 1141.4, TfNSW TS 02799.10, TfNSW TS 02799.11 | |||
Shape | Average least dimension; Flakiness; Proportional calliper; Ratio greatest to least dimension | AS 1141.14, AS 1141.15, AS 1141.20.1, AS 1141.20.2, TfNSW TS 02799.12, TfNSW TS 02799.32, TfNSW TS 02799.50 | |||
Particle size distribution | Sieve analysis of material finer than 75 µm | AS 1141.12, RMS (NSW) Method T203 TfNSW TS 02799.04 | |||
Evaluation of geotechnical and civil construction material - Aggregate strength | Aggregates | Wet/dry strength variation | Not applicable | AS 1141.22, TfNSW TS 02799.13 | |
Evaluation of geotechnical and civil construction material - Concrete, grout and mortar consistence in situ | Concrete, grout and mortar | Slump flow | Cone | AS1012.3.1, RMS (NSW) Method T301 TfNSW TS 02800.02 | |
Evaluation of geotechnical and civil construction material - Concrete, grout and mortar properties | Concrete, grout and mortar | Compressive strength | Core; Cube; Cylinder | AS 1012.9, AS 1012.14, RMS (NSW) Method T306, RMS (NSW) Method T375 TfNSW TS 02800.07,TfNSW TS 02800.49 | |
Mass per unit volume - Hardened concrete | Dimensions; Water displacement | AS 1012.12.1, AS 1012.12.2, RMS (NSW) Method T316, RMS (NSW) Method T317 TfNSW TS 02800.16,TfNSW TS 02800.17 | |||
Specimen preparation | Capping of compressive strength specimens | RMS (NSW) Method T305 TfNSW TS 02800.06 | |||
Air content of freshly mixed concrete | Reduced air pressure | AS 1012.4.2, RMS (NSW) Method T320 TfNSW TS 02800.20 | |||
Evaluation of geotechnical and civil construction material - Concrete, grout and mortar specimen manufacture and curing | Concrete, grout and mortar | Specimen conditioning | Wet conditioning of hardened concrete core specimens | AS 1012.14 | |
Specimen manufacture and curing | Curing cylinder specimens in the laboratory; Curing grout and mortar cube specimens in the laboratory; In situ manufacture and curing of cylindrical specimens | AS 1012.8.1, RMS (NSW) Method T375 TfNSW TS 02800.49 | |||
Evaluation of geotechnical and civil construction material - Road pavement structural performance | Road pavements | Structural performance evaluation | Benkelman beam; Deflection monitoring | RMS (NSW) Method T160, TfNSW T199; TfNSW TS 02795.22,TfNSW TS 02795.55 | |
Evaluation of geotechnical and civil construction material - Soil classification | Soils | Sieve analysis | Not applicable | AS 1289.3.6.1, TfNSW T106; RMS(NSW) Method T106 TfNSW TS 02795.02 | |
Liquid limit | Casagrande one point | AS 1289.3.1.2 | |||
Liquid limit | Casagrande four point | AS 1289.3.1.1, TfNSW T108 TfNSW TS 02795.04 | |||
Plastic limit | Not applicable | AS 1289.3.2.1, TfNSW T109 TfNSW TS 02795.05 | |||
Plasticity index | Casagrande | AS 1289.3.3.1, TfNSW T109 TfNSW TS 02795.05 | |||
Moisture content | Drying oven | AS 1289.2.1.1, RMS (NSW) Method T120 TfNSW TS 02795.14 | |||
Linear shrinkage | Not applicable | AS 1289.3.4.1, TfNSW T113; TfNSW TS 02795.08 | |||
Fine particles in road materials | Not applicable | TfNSW T107; RMS(NSW) Method T107 TfNSW TS 02795.03 | |||
Evaluation of geotechnical and civil construction material - Soil compaction characteristics | Soils | Dry density/moisture content relationship | Modified compactive effort | AS 1289.5.2.1, RMS (NSW) Method T112 TfNSW TS 02795.07 | |
Assignment of optimum moisture content/maximum dry density (OMC/MDD) | Not applicable | AS 1289.5.4.2 | |||
Dry density/moisture content relationship | Three compaction point | RMS (NSW) Method T162 TfNSW TS 02795.24 | |||
Dry density/moisture content relationship | Standard compactive effort | AS 1289.5.1.1, RMS (NSW) Method T111, RMS (NSW) Method T130 TfNSW TS 02795.06,TfNSW TS 02796.01 | |||
Evaluation of geotechnical and civil construction material - Soil dispersion | Soils | Dispersion | Emerson class | AS 1289.3.8.1 | |
Evaluation of geotechnical and civil construction material - Soil field density | Soils | Density - In situ | Sand pouring apparatus | RMS (NSW) Method T119 TfNSW TS 02795.13 | |
Compaction control | Hilf | AS 1289.5.7.1 | |||
Moisture ratio | Measured | AS 1289.5.4.1 | |||
Relative compaction | RMS (NSW) Method T166 TfNSW TS 02795.28 | ||||
Dry density ratio | Calculation | AS 1289.5.4.1 | |||
Density - In situ | Nuclear gauge | AS 1289.5.8.1, RMS (NSW) Method T173 TfNSW TS 02795.36 | |||
Evaluation of geotechnical and civil construction material - Soil laboratory bearing properties | Soils | Bearing ratio | Remoulded specimens | AS 1289.6.1.1, RMS (NSW) Method T117, RMS (NSW) Method T132 TfNSW TS 02795.11,TfNSW TS 02796.03 | |
Evaluation of geotechnical and civil construction material - Soil pre-treatment | Soils | Soil pre-treatment | Accelerated weathering pre-treatment; Repeated compaction pre-treatment | TfNSW T102; TfNSW T103 TfNSW TS 02794.02,TfNSW TS 02794.03 | |
Soil pre-treatment | Not applicable | AS 1289.1.1, TfNSW T105; TfNSW TS 02795.01 | |||
Evaluation of geotechnical and civil construction material - Soil stabilisation | Soils | Compressive strength | Uniaxial unconfined | RMS (NSW) Method T116, RMS (NSW) Method T131 TfNSW TS 02795.10,TfNSW TS 02796.02 | |
Sample collection | Aggregates | Not applicable | Aggregate from a bin; Aggregate from a stockpile; Aggregate from a truck | AS 1141.3.1, RMS (NSW) Method T100 TfNSW TS 02794.01 | |
Concrete, grout and mortar | Not applicable | Fresh concrete from a mixer; Fresh concrete from deposited concrete | AS 1012.1 | ||
Soils | Not applicable | Disturbed soil sampling from a pavement; Disturbed soil sampling from a stockpile; Disturbed soil sampling from a windrow; Disturbed soil sampling in situ | AS 1289.1.2.1, RMS (NSW) Method T100 TfNSW TS 02794.01 |
ISO/IEC 17025 (2017)
Infrastructure and Asset Integrity
Service | Product | Determinant | Technique | Procedure | Limitations |
---|---|---|---|---|---|
Annex facility | Materials defined by all or some for which the site is accredited | Determinations defined by all or some for which the site is accredited | Techniques defined by all or some for which the site is accredited | Monaro Highway Upgrade Annex Facility, site no. 26642, is established from 18 March 2024 until 30 November 2025 for Monaro Highway Upgrade - Lanyon Drive Interchange and Associated Works for Package 1B Services - Hume, ACT project for Woden Contractors Pty Ltd, Contract number P208281.19 |
The only data displayed is that deemed relevant and necessary for the clear description of the activities and services covered by the scope of accreditation.
Grey text appearing in a SoA is additional freetext providing further refinement or information on the data in the preceding line entry.
Accreditation No.
828
Site No.
21921
Print date
26 Nov 2024